BritNed: Great Britain to the Netherlands

BritNed is an undersea power cable between Great Britain and the Netherlands, from Isle of Grain, Kent, to Maasvlakte, near Rotterdam. It can carry 1,000 MW, the joint 4th largest of Great Britain's 10 interconnectors, and opened in 2011.

1,000 MWcapacity
260 kmlength (about)
2011opened
9.7%of Great Britain's interconnector capacity

See BritNed's flow right now, every 5 minutes, on the live dashboard (Great Britain's Interconnectors card), or on the Live map.

Recent flows

On 28 October 2026 (the 22.9 hours to 22:55 UK time), Great Britain exported 8.9 GWh over BritNed to the Netherlands, an average of 389 MW, 39% of its capacity.

Key facts

ConnectsGreat Britain and the Netherlands
RouteIsle of Grain, Kent, to Maasvlakte, near Rotterdam
Capacity1,000 MW
TechnologyHigh-voltage direct current, ±450 kV
Lengthabout 260 km
Opened2011
OwnerBritNed Development (National Grid and TenneT)

Questions and answers

What is BritNed?

BritNed is a high-voltage power cable between Great Britain and the Netherlands, running from Isle of Grain, Kent, to Maasvlakte, near Rotterdam. It can carry 1,000 MW, 9.7% of Great Britain's interconnector capacity, and opened in 2011.

How much power can BritNed carry?

1,000 MW: the joint 4th largest of Great Britain's 10 interconnectors. That is about 9.7% of the 10,304 MW all of them can carry together.

How long is BritNed?

About 260 km: the 4th longest of Great Britain's interconnectors.

Who owns BritNed?

BritNed Development (National Grid and TenneT).

When did BritNed open?

In 2011, so it has been running for about 15 years.

Where can I see BritNed's flow now?

The Global Grid dashboard shows BritNed's flow every 5 minutes, from Elexon's figures: whether Great Britain is importing or exporting, and how much.

Great Britain's other interconnectors

InterconnectorToMWOpened
IFAFrance2,0001986
North Sea LinkNorway1,4002021
Viking LinkDenmark1,4002023
IFA2France1,0002021
ElecLinkFrance1,0002022
Nemo LinkBelgium1,0002019
GreenlinkIreland504early 2025
East-WestIreland5002012
MoyleNorthern Ireland5002001

Every UK interconnector, with the UK's imports since 2000 and the cables being built

Sources: the cables' owners and operators (capacities, routes and opening dates, as on the Pipelines tab's power link details); the flows on the live dashboard contain BMRS data © Elexon Limited copyright and database right; the United Kingdom's net imports are Ember's yearly electricity data (CC BY 4.0). Facts checked 28 October 2026.

To cite this page: Global Grid, “BritNed: Great Britain to the Netherlands”, globalgrid.uk/interconnector/britned, and the original source named above.